Past project · Bathroom · Updated
Summit Hill Bathroom Remodel
- On site
- 10 weeks
- Where
- Summit Hill, St. Paul
- House built
- 1911
At 2026 pricing, a bathroom like this one, in a 1911 house in St. Paul’s Summit Hill neighborhood, falls in our high-end tier, $80,000 and up. Construction took 10 weeks on site to final inspection, from Tuesday, June 6, 2023, to the City of St. Paul final building, plumbing and mechanical inspections the week of August 7. A laundry-pan fix and the last details ran into week 12. Owner Kim Studham ran the job.
- The wall between a cramped second-floor hall bath and a windowless laundry closet came out. That made one room about 8 feet 8 inches by 9 feet 9 inches between the framing.
- Notched floor joists were reinforced, and all-new plumbing, with recirculating hot water, was run above a dining room with a coffered ceiling with stained wood detailing, tall stained crown molding and tall wainscoting.
- The cast-iron radiator came out. A thermostat-controlled electric baseboard heater, which meets code for heat in a finished space, now heats the room. Electric in-floor heat under the tumbled marble octagon floor is supplemental comfort heat, never the heat source.
- The old tub had an above-floor drain. A joist turned out to sit where the new tub’s drain needed to go. Reframing that joist is a common, straightforward fix, but the family didn’t want the dining room below disturbed, so the new tub’s drain also sits above the subfloor. It’s still a good tub for bathing.
At a glance
- Project
- a hall bathroom and a laundry closet combined into one room
- Where
- Summit Hill neighborhood, St. Paul, Minnesota
- House
- built 1911, stucco, three finished floors
- Room size
- about 8 feet 8 inches by 9 feet 9 inches after demolition, roughly 85 square feet
- 2026 estimated cost
- $80,000 and up (high-end tier)
- On site
- 10 weeks to final inspection (9 planned), June 6 to the week of August 7, 2023; last details early in week 12
- Design to finish
- about 8 months, December 2022 to August 2023
- Permits
- City of St. Paul building permit, city plumbing and mechanical inspections, a state electrical inspection and an in-floor heat cable inspection; finals passed the week of August 7, 2023
- Layout changed
- yes; the non-load-bearing wall between the bath and the laundry closet came out
- Lived at home
- yes; the house had another bathroom
The home
A 1911 house in St. Paul’s Summit Hill neighborhood, with a stucco exterior and three finished floors.
The second-floor hall bath had a pedestal sink, a cast-iron radiator under the window, a tub with a curtain and a white hex tile floor. The floor had cracked across where a hot-water line ran through the thick concrete bed under the old tub. The toilet sat tight to the tub.
Next door, behind its own door off the hall, a narrow, windowless closet held a stacked washer and dryer. The laundry ran on the downstairs electrical panel, which the family wanted freed up for the kitchen. Directly below is the dining room, with a coffered ceiling with stained wood detailing, tall stained crown molding and tall wainscoting the family did not want disturbed.
The family wanted:
- a low-entry tub with a support bar, and tile on the ceiling over the tub
- recirculating hot water
- heated floors plus a quiet room heater
- a dark wood vanity with an open bottom shelf, and a black top with a rectangular undermount sink and tall faucet
- an ironing-board cabinet
- a new window with privacy glass below and clear glass above “so we could see the treetops”
- a floor that matched the octagon tile in their other bathroom on the same floor
They kept a tub so the house would still have one.
Two years later the same family hired Prima for their kitchen.
We describe homes by town and era only. Client names and addresses stay private.

Before photos and floor plan




Plans

What did this St. Paul bathroom remodel cost?
At 2026 pricing, a bath like this falls in our high-end tier, $80,000 and up. Prima bathrooms from $30,000. Our bathroom ideas-and-costs page groups baths in three tiers: midrange, $30,000–$40,000, typically 4–7 weeks; upscale, $50,000–$70,000, typically 5–8 weeks; and high end, $80,000 and up, typically 10+ weeks. This one is high end: a wall removed, structural repair, all-new plumbing, a new electric heater, a laundry folded into the same room, and stained wood trim. Every Prima project gets a fixed price in writing after a site visit, before construction starts.
What drove the cost?
Shares are of the construction contract (see “The contract, line by line”).
- 01Plumbing, 13.2%The largest cost line. All-new supply and drain lines, run back toward the source as far as possible without work in other rooms, plus the planned openings below. It includes the plumbing fixtures and an extension of the house’s recirculating hot water.
- 02Walls, ceiling and framing, 11.6%This covers five lines:
- new walls drywalled, 5.5%
- the ceiling, 2.2%
- wall framing, 2.2%
- exterior-wall insulation, 1.1%
- opening the floor framing for the trades, 0.6%
- 03Electrical, 8.8%The laundry circuit moved off the downstairs panel. All-new service for the room comes from the upstairs subpanel, with two recessed lights and a sconce allowance.
- 04Heat and air, 7.8%An electric baseboard heater and in-floor comfort heat, 3.9%. HVAC work, 3.9%: the radiator removed with the boiler drained and refilled, heating rough-in, and an air-conditioning duct run down to the dining room, which had no air conditioning, while the walls were open.
- 05Tile, 7.3%Shower walls and the ceiling over the tub, 4.6%; the marble floor, 2.7%.
- 06Vanity, top, mirror, sink and faucet, 6.6%,plus a refinished door and wood baseboard, 1.1%.
Part of every price is craftsmanship a line on a quote doesn’t show: on this job, the notched joists were reinforced on each side with 3/4-inch plywood that we pre-cut, glued with construction adhesive and structurally screwed, before the new pipes went in. What’s in a Prima price that a cheaper quote doesn’t include.
Finished photos









How long did it take?
10 weeks on site to final inspection, one more than planned, and about 8 months from the first visit to the last details.
Planned: 9 weeks. The week 1 review (June 10) put inspections, load-out and cleaning in week 9, starting July 31. Actual: construction started Tuesday, June 6, 2023. Final inspections passed in week 10, one week later than planned: plumbing on Wednesday, August 9, and mechanical and building the same week. The last details were done early in week 12.
What moved it:
- Extra joist repair in week 2 pushed the heating rough-in by a day.
- The new window came from the factory with its glass reversed (privacy pane on top). It went in on schedule ahead of tile and trim, and replacement sashes were swapped in during week 10.
- The washer shook at spin after the laundry was hooked up. The first pan came out and the plumber installed a longer one in week 11.
- One cracked floor tile, found after completion, was replaced September 14.
Before construction
- December 2022first visit and design concept; before photos and a scan of the rooms (December 29–30).
- January 2023design agreement (January 2); measured layout; design meeting with Scott over Zoom; plumbing review; tile research to match the other bath on the floor.
- February–March 2023layout updates; selections tracked; construction contract and drawings (March 30–31) and deposit.
- April–May 2023selections due by item from April 1 to June 1; design board (May 9–10) and pre-construction meeting (May 10); building permit application and permit drawings (May 16); window ordered (May 31).
Week by week
- Week 1 (June 5; start Tuesday, June 6)home protected; demolition started; gas dryer discovered.
- Week 2 (June 12)demolition finished, including the concrete under the old tub, with the water shut off; framing; insulation and vapor barrier on the tub’s exterior wall; joist repair and plumbing rough-in; tub changed to clear a joist; post-demo measurements sent for the plan update.
- Week 3 (June 19)heating and electrical rough-in; electrical inspection passed; insulation, vapor barrier and fire blocking.
- Week 4 (June 26)plumbing, radiator, heating and framing inspections all passed Monday; tub and laundry pan installed; subfloor; drywall.
- Week 5 (July 3, closed Monday–Tuesday)primer in the bath and on the dining-room ceiling panel; in-floor heat mats; shower walls prepped for tile; tile started; window installed.
- Week 6 (July 10)in-floor heat cable installed and inspected; tile continued; bath painted.
- Week 7 (July 17)tile finished except pieces that meet the trim; shower and floor grouted; vanity and grab bar installed.
- Week 8 (July 24)trim started; remaining tile; electrical finish; washer and dryer delivered.
- Week 9 (July 31)trim; countertop; door fitted and refinished; plumbing finish; hallway wall painted.
- Week 10 (August 7)trim finished; window sashes replaced; mirror and accessories; final mechanical, plumbing and building inspections passed.
- Week 11 (August 14)washer and dryer moved out; tile lifted; plumber installed a longer laundry pan.
- Week 12 (August 21)mirror frame, door, last details; site protection removed.
- September 14cracked floor tile replaced.
The job, line by line
- Layout
- the non-load-bearing wall between the hall bath and the laundry closet came out, making one room in the same footprint. The doorway to the old laundry closet was walled in, and the spare door went to the basement.
- Structure/framing
- notched joists reinforced with 3/4-inch plywood, glued and screwed. Blocking for the grab bars, and fire blocking.
- Mechanical/HVAC
- cast-iron radiator removed, with the boiler system drained and refilled. Heating and air-conditioning rough-in, inspected in week 4. Panasonic WhisperQuiet bath exhaust fan, Prima’s standard.
- Plumbing
- all-new supply and drain lines replacing a mix of copper, galvanized and plastic pipe.
- the house’s recirculating hot water extended to the bath
- tub with an above-floor drain
- pressure-balanced shower valve with a 3-function diverter, feeding a showerhead and a slide-bar hand shower
- comfort-height toilet and undermount sink
- laundry pan, replaced with a longer one in week 11
- Electrical/lighting
- laundry circuit moved off the downstairs panel, with new service from the upstairs subpanel. Two LED recessed lights, a vanity light, and a dedicated vanity outlet wired early so the crew could run tools from it. A thermostat-controlled electric baseboard heater, and electric in-floor comfort heat with its own wall thermostat.
- Cabinets/vanity
- 30-inch single vanity in dark wood with an open bottom shelf. The planned ironing-board cabinet couldn’t be recessed and would have stood about 7 inches off the wall, so it was returned for a credit.
- Counters
- black Vicostone Java Noir quartz, a remnant piece.
- Backsplash/tile
- shower walls and the ceiling over the tub in Hall Blanco white ceramic tile, 8 by 20 inches, with Arctic White grout, a black polished accent strip at shoulder height and two Carrara corner shelves.
- Floors
- joist bays cleaned out, new subfloor and cement board. Tumbled marble 3-by-3-inch octagon mosaic with black dots, Cape Gray grout, over electric in-floor heat. An extra box of tile was left for future repairs.
- Walls/paint
- Sherwin-Williams Alabaster (SW 7008), Duration Home interior, satin, on the walls. The dining-room ceiling panel and the upstairs hallway wall were repainted.
- Windows/doors
- new Andersen 400 Series tempered double-hung window, privacy glass in the lower sash and clear glass above, with sashes swapped in week 10. Original door stripped, repaired and restained, with its swing reversed. The tall wood baseboards, the window and door casing and the refinished door were stained to match the existing woodwork in the hall, so the bath blends with the rest of the house.
- Appliances
- new stackable electric washer and dryer, bought by the homeowners and delivered upstairs.
- Fixtures
- Hansgrohe Metris S faucet, Delta Galeon shower trim, Kohler Santa Rosa toilet, and an Oasis BA-R-41 tub with an above-floor drain in place of the old cast-iron tub.
- Hardware
- brushed-nickel grab bars; toilet paper holder, two hooks, towel bar and a curved shower curtain rod.
- Ventilation
- Panasonic WhisperQuiet bath exhaust fan, Prima’s standard.
- Heat
- a thermostat-controlled electric baseboard heater, replacing the cast-iron radiator; it meets code for heat in a finished space. The electric in-floor heat is supplemental comfort heat; it is never the room’s heat source.
- Added mid-job
- a different tub to clear a joist, a longer laundry pan, and an extra box of floor tile. One credit at the final invoice, for the returned ironing-board cabinet.
- Permits & inspections
- St. Paul building permit, applied for May 16, 2023 to “remodel existing laundry/bathroom by removing non-load wall between two rooms.”
- City plumbing and mechanical inspections, a state electrical inspection, and an in-floor heat cable inspection in week 6.
- All rough-ins passed by June 26; finals passed the week of August 7.
The contract, line by line
The construction contract (March 30, 2023) has 19 lines. Each line shows its share of the contract total, not a dollar figure. At 2026 pricing the whole bath falls in our high-end tier, $80,000 and up.
Line shares are at Prima’s cost. Project management, overhead and salary are shown as their own line, a 42% markup on cost.
| No. | Trade (cost code) | What the contract says | Allowance named in the line | Share of contract |
|---|---|---|---|---|
| 1 | Plans & permits (01) | Construction drawings, permits and inspections. | — | 3.3% |
| 2 | Site work (02) | Site prep, site protection, dumpster service. | — | 2.2% |
| 3 | Demolition (02.1) | Demolition of the existing space per the drawings. | — | 3.5% |
| 4 | Floor framing (06) | No major change to the floor framing; open the floor so the plumbing and HVAC can be installed. | — | 0.6% |
| 5 | Wall framing (07) | Framing of walls per the drawings. | — | 2.2% |
| 6 | Windows & trim (13) | New window per the drawings. | — | 2.2% |
| 7 | Insulation (17) | Insulation of the exterior walls. | — | 1.1% |
| 8 | Interior walls (18) | New walls, drywall finished flat. | — | 5.5% |
| 9 | Ceilings (19) | Ceiling, drywall finished flat. | — | 2.2% |
| 10 | Tile (21.3) | Tile the shower walls and the ceiling over the tub, including backer board. | — | 4.6% |
| 11 | Tile (21.3) | Tile the bathroom floor. | — | 2.7% |
| 12 | Specialty (22) | Bathroom accessories: toilet paper holder, two hooks, shower grab bar, shower curtain rod, towel bar. | — | 1.7% |
| 13 | Specialty (22) | In-floor heat, plus a wall or baseboard heater. | — | 3.9% |
| 14 | Millwork & trim (20) | Refinish the door per the drawings; wood baseboard. | — | 1.1% |
| 15 | Cabinets & counters (21) | Vanity, countertop, mirror, sink and faucet per the selections. | — | 6.6% |
| 16 | Plumbing (14) | All-new plumbing in the bathroom, updated back toward the source as far as possible without work in other rooms (except the openings downstairs shown on the drawings). Includes the plumbing fixtures. Recirculating hot water. | — | 13.2% |
| 17 | HVAC (15) | HVAC work per the drawings. | — | 3.9% |
| 18 | Electrical & lighting (16) | Move the washer/dryer circuit off the downstairs panel and run all-new service for the bathroom from the upstairs subpanel. Two recessed lights and a sconce allowance. | Allowance: sconce | 8.8% |
| 19 | Paint (24) | Prime and paint the room. | — | 1.1% |
| Project management, overhead and salary (42% markup on cost) | — | — | 29.6% | |
| Total | 100.0% |
What changed during construction?
One change order: a credit at the final invoice of −0.2% of the contract, for returning the ironing-board cabinet. Like the contract lines, it is shown at Prima’s cost; the same 42% markup on cost applies to it. The tub changed to clear a joist, the laundry pan was replaced with a longer one, and an extra box of floor tile was left for repairs.
Payment schedule
- 10.0% at signing
- 30.0% on the first day of work
- 30.0% at the framing inspection
- 30.0% at the final inspection
What isn’t included?
- The washer and dryer (the homeowners bought them).
- Work in other rooms, beyond the openings below shown on the drawings.
- Exterior trim and stucco around the new window.
- Clearing the rooms and protecting belongings from dust.
- Anything an allowance doesn’t cover. The sconce had an allowance; going over it is added at the end, and anything left over is credited.
Selections
- Floor tile
- Hampton Hermosa tumbled marble octagon, 3 by 3 inches, matching the family’s other bath. The plans at contract time called for a porcelain look-alike that wasn’t slippery. The family switched to real marble knowing it needs care.
- Shower
- Delta Galeon pressure-balanced trim with an integrated 3-function diverter, and two Carrara corner shelves.
- Accent tile
- Noir polished Somerset strip at about shoulder height.
- Faucet
- Hansgrohe Metris S, 1.2 GPM, single hole.
- Toilet
- Kohler Santa Rosa, comfort height, white.
- Vanity
- 30-inch Morris single vanity with a white rectangular undermount sink.
- Mirror
- unfinished oak frame, stained on site to match the vanity.
- Grab bars
- brushed nickel, anchored to blocking.
- Heat
- electric baseboard, chosen for quiet, plus electric in-floor heat for comfort.
- Exhaust fan
- Panasonic WhisperQuiet, Prima’s standard.
- Shower wall tile
- Hall Blanco ceramic, 8 by 20 inches, from The Tile Shop; Fusion Pro Arctic White grout.
- Floor grout
- Prism Cape Gray.
- Counter
- Vicostone Java Noir quartz remnant.
- Tub
- Oasis BA-R-41, above-floor drain.
- Window
- Andersen 400 Series, tempered double-hung, privacy glass low and clear glass high.
- Paint
- Sherwin-Williams Alabaster SW 7008, Duration Home, satin.
- Where and when
- selections were due between April 1 and June 1, 2023, item by item. Shower wall tile options were still being sourced in April; the Hall Blanco tile from The Tile Shop was selected May 14, and the window was ordered May 31.
What to know about remodeling a bathroom in a 1911 St. Paul house
Kim’s advice for anyone redoing a bathroom in a house this age:
- Replace every line that feeds the bathroomPlumbing, electrical and any radiant heat, before the finishes go in. “…this is the time to update all of this … before you put in all the nice finishes.”
- Plan for the floor to come upThe joists have to be checked before tile goes down. “You don’t want to do all this new bathroom work, especially this marble floor, and have joists that are compromised from old work being done.” Leveling an old floor usually leaves a transition at the doorway.
- An upstairs bath needs a route downNew drain and supply lines have to pass through the main floor, and today’s code sometimes calls for larger pipe than the old lines. Here we planned openings in the dining-room ceiling below and were ready to make them, but the drain ran differently and they weren’t needed. Substantially more subfloor work, joist repair and floor leveling offset that.
- Moving a fixture means meeting today’s clearancesCode sets the space in front of each fixture. If you don’t relocate fixtures, the work counts as a repair: a new toilet, sink, faucets and shower trim, and refinished surfaces. Relocate or add a fixture (adding a shower, or moving the toilet, as we did here) and it has to meet current code clearances. In this bath the toilet sat so close to the tub that “…even a modest size height person would hit their knees on the bathtub.”
- New pipe brings back water pressureOld galvanized supply pipe corrodes from the inside, so less and less water gets through, sometimes until it clogs. “Your water pressure is going to be drastically improved once … you have new piping coming up to the bathroom.”


What turned up in this one:
- The concrete and the water linethe old tub sat on thick concrete, with a hot-water line running through it just under the floor tile. Years of heating and cooling in that line had cracked the floor. The water was shut off for the concrete demolition.
- Pipes from every eracopper, galvanized and plastic. Burlap-type stitched insulation sat alongside spray foam, batts and blown-in insulation.
- Notched joistsdecades of plumbing had cut into the joists. Before the plumbing rough-in, we pre-cut 3/4-inch plywood and had high-quality construction adhesive ready to sister both sides of each joist. The plumbers take out the old lines first and pick their routes, so reinforcing earlier could block them. The plywood is glued and structurally screwed to the joists before the new pipes go in, because afterward there’s often no room for a drill.
- A main stack that joggedthe main sewer stack jogged in a way we didn’t expect instead of dropping straight down, so the new drain tied into an existing vertical stack without opening the dining-room wall or the main floor below.
- The real room sizeafter demolition the room measured 8 feet 8 inches along the tub and 9 feet 9 inches along the window wall. Kim asked for the plan to be updated to those numbers because walls might need furring for pipes. In week 4 the wall behind the vanity was furred out: a 2×4 wall in front of the insulated exterior wall, to carry the supply lines and the air-conditioning run. The tub wall was not furred out.
- A gas dryerthe plans assumed an electric dryer, but it was gas. The family chose a new electric stackable pair.
- A drain over a joistthe tub the family picked needed its drain right where a floor joist sat, which we didn’t know beforehand, and code doesn’t allow notching it.
- A reversed windowthe new window arrived with the privacy glass on top, though it was ordered correctly. It went in on schedule, and the sashes were swapped when replacements came.
- Unusual framingthe wall planned for the ironing-board cabinet had been reframed in an earlier renovation. Recessing the cabinet would have damaged the room on the other side.
- A pine doorunder the paint, the door frame was pine, not oak, so the stain was worked to come as close as possible to the oak trim.
- The dining-room ceilingduring demolition a hole opened in the dining-room ceiling, at the spot where the new air-conditioning duct was going through. It was repaired with the bath drywall.
What did the family choose, and why?
- One room instead of twoAn earlier owner had moved the laundry up from the basement into the hall closet. The closet was too narrow to stand in and the bath was too small, but growing past the two rooms would have cut into the bedrooms on either side. Kim: “…routing plumbing this far across floor joists would have been problematic and potentially compromise the beautiful coffered ceilings on the main floor.” So the wall between them came out and everything stayed inside the combined footprint, with a marble floor and the same stained wood as the rest of the house: “…the same wood, rich wood stain from the rest of the house really tied it in to make it feel like it had always been there.”
- The tubOne option was to move the wall behind the tub to get the drain off the joist, but in a room this small that caused other clearance and code problems. Reframing that joist is a common, straightforward fix, but the family didn’t want the dining room below disturbed. The other option was a tub with an above-floor drain, the way the old one was built. It sits a little higher and is still good for bathing, it was in stock, and it kept the schedule. The family chose it the same evening.
- Floor tileA porcelain look-alike (the plan at contract time) or real tumbled marble to match the other bath. They chose marble.
- Washer and dryerKim recommended a new electric dryer with a matching washer, delivered upstairs and in place by July 25 so they could be installed during the project.
- Ironing-board cabinetThe plan was to recess it if possible, otherwise surface-mount it. Surface-mounted, it would have stood about 7 inches off the wall, into the door swings and the toilet area. The family decided against forcing it in.
- Exterior window trimConsidered as a change order and left out: the window installer confirmed it couldn’t be done without a high chance of damaging the stucco.
- Laundry panThe plumber’s first fix for the shaking washer didn’t work, so the pan was replaced with a longer one that fit the space better.
- PaintSherwin-Williams Alabaster in satin.
- HeatElectric baseboard instead of a radiator, for floor space and quiet, with in-floor heat added for comfort.
Can you live at home during a bathroom remodel?
The family lived at home throughout, with their dogs, and the crew kept working while they were away for two weeks in July. The house had another bathroom in use.
- The dumpster went on the street, so the family kept the driveway.
- Tile cutting happened on an upper deck. Its rubber roof sits over a family room, so the crew covered the deck with 1/8-inch masonite.
- Tools ran off an outdoor outlet, batteries and the new vanity outlet. Materials were staged in the neighboring bedroom.
- Water shutoffs came with a text warning to whoever was home.
- Dust barriers went up for the work in the dining room and upstairs hallway, and the dining-room protection came down in week 5 once its ceiling was painted.
- The bath was out of use from June 6 until after final inspection. The laundry was out longer: the pan rework meant laundromat trips into mid-August.
In Kim’s words
“The bathroom experience is way more comfortable, and the laundry experience is way more comfortable.”
“…she just really trusted me, and then I could make a recommendation. And she was decisive… Even … if there was a little hiccup, I told her the plan to fix it…”
Behind the old walls the crew found an electrician’s business card from 1989. Kim generally signs the studs on a project with Prima’s name and the year. “…it’s fun to find those little notes from other contractors that worked on the home over the years… It was rewarding to add to the story of it.”

— Kim Studham, owner, Prima Construction; two college degrees in architecture. Prima is woman-owned.
What every Prima contract covers
- A fixed price in writingThe price is set before work starts. It changes only by a written change order, and email counts. Each change order is priced and approved in writing before that work begins.
- Prima pulls the permitsThe job closes, and final payment is due, when the city passes the final inspection.
- Payments follow milestonesOn this job: deposit, first day of work, framing inspection, final inspection. Lien waivers from subcontractors and suppliers are available on request.
- Allowances settle at the endSpend less than an allowance and the difference is credited. Spend more and it’s added.
- Minnesota’s statutory warrantyIt covers 1 year for workmanship and materials; 2 years for plumbing, electrical, heating and cooling installation; and 10 years for major construction defects. Manufacturers’ warranties pass to you.
Frequently asked questions
How much does a bathroom remodel like this cost in St. Paul?
At 2026 pricing, a bath like this one in a 1911 Summit Hill house falls in Prima’s high-end tier, $80,000 and up: a wall removed to fold a laundry closet into the bath, reinforced joists, all-new plumbing with recirculating hot water, in-floor comfort heat under a marble floor, and stained wood trim. Prima bathrooms from $30,000. Your number is a fixed price in writing after a site visit.
How long does a high-end bathroom remodel take in an old St. Paul house?
This 1911 St. Paul bath took 10 weeks on site to final inspection, from June 6 to the week of August 7, 2023, against a 9-week plan, with the last details early in week 12. Design and selections took about five months before that.
Do we have to move out during a bathroom remodel?
No. This St. Paul family stayed home for the whole job and used their other bathroom. The bath was out of use for the whole job and the laundry a little longer, into mid-August, while a longer washer pan went in.
What permits does a bathroom remodel need in St. Paul?
This St. Paul bathroom had a city building permit, city plumbing and mechanical inspections, a state electrical inspection, and an inspection of the in-floor heat cable before tile went down. All rough-ins passed by June 26, 2023, and the finals the week of August 7.
Can you combine a laundry closet and a bathroom?
Yes, when neither room works on its own and growing past them would cost other rooms. In this 1911 St. Paul house a too-narrow laundry closet and a too-small hall bath sat between bedrooms, so the non-load-bearing wall between them came out and the stacked washer and dryer now sit on a pan in the bath, about 8 feet 8 inches by 9 feet 9 inches. Staying in the footprint also kept new plumbing from running far across the joists over the main-floor ceilings. The laundry circuit moved to the upstairs subpanel, and a longer pan steadied the washer.
What replaces an old radiator in a bathroom remodel?
In this 1911 St. Paul bath the cast-iron radiator came out and the boiler was drained and refilled. A quiet, thermostat-controlled electric baseboard heater now heats the room and meets code for heat in a finished space. Electric in-floor heat under the tumbled marble octagon floor is supplemental comfort heat, never the room’s heat source. The heat cable passed its inspection in week 6.
What should you plan for when remodeling a bathroom in a 100-year-old house?
Plan to replace every line that feeds the bathroom (plumbing, electrical and any radiant heat) before the finishes go in. Plan for the floor to come up so the joists can be checked and the floor leveled, which often leaves a transition at the doorway. An upstairs bath needs a route for new pipe down through the main floor, sometimes in larger sizes than the old lines, and any fixture that moves has to meet today’s code clearances. In this 1911 St. Paul bath that meant all-new supply and drain lines, notched joists reinforced with 3/4-inch plywood, and planned openings in the dining-room ceiling below that the drain’s actual path made unnecessary.
Will new plumbing improve water pressure in an old house?
Usually, yes. Old galvanized supply pipe corrodes from the inside, so less and less water gets through, sometimes until it clogs. Replacing it with new supply lines up to the bathroom drastically improves the water pressure there. This 1911 St. Paul bath replaced a mix of galvanized, copper and plastic with all-new supply and drain lines.
Related
- Bathroom remodeling with Prima and our bathroom ideas and costs, with every tier priced
- Remodeling St. Paul’s historic homes
- Kitchen remodel costs in Minneapolis–St. Paul, 2026
- A primary bath with an old fireplace taken out: Edina kitchen and bath remodel
- Request a visit for a fixed price in writing
Sources: price from the high-end tier on Prima’s bathroom ideas-and-costs page (November 2026); year built from public property records; neighborhood from the Summit Hill Association’s district boundaries; line shares and payment schedule from the 2023 construction contract; dates from Prima’s weekly job reports; scope from the permit drawings, the selections sheet and job emails.
What would yours cost?
Kitchens from $80,000; bathrooms from $30,000. Kim sees the space, then you get a fixed price in writing.